Project Profile: Bovey Complex Masonry Repairs & Window Replacement

  Bovey Building Masonry and Window Repairs, Photo 1

Bovey Building Masonry and Window Repairs, Photo 2

Bovey Building Masonry and Window Repairs, Photo 3

Bovey Complex Masonry Repairs & Window Replacement

Project: 621102

Project Description: Repairs to the brick and windows on the Bovey Buildings. Work will be broken out into 2 phases to deal with evolving supply chain challenges.

Construction Value: $2,600,000.00

Construction Completion Date: August 2023

Prime Consultant: Read Jones Christoffersen Ltd.

Masonry Contractor: Colonial Building Restoration

Window Contractor: TBD

Physical Resources, Project Manager: Wes Johnson

Physical Resources, Senior Construction Coordinator: David Loates