Project Profile: 2021 Tunnel Repairs
Project Title: 2021 Tunnel Repairs
Project: 621099
Project Description: Extensive structural and waterproofing repairs to Tunnel 3 beneath Reynolds Road, and Tunnel 4 beneath Stadium Walk.
Construction Value: $3,900,000
Construction Completion Date: September 2021
Prime Consultant: Walter Fedy
General Contractor: Collaborative Structures Limited
Physical Resources, Project Manager: Justin Selby
Physical Resources, Construction Coordinator: Eric LaFontaine